Miami-Dade County commissioners voted in January 2026 to pour an additional $15.5 million into oversight of the stalled Metromover upgrade, with officials now projecting the $153 million overhaul will not be finished until 2028 or 2029 — three to four years past the original May 2025 target.
Why is the Metromover upgrade running so far behind schedule?
The overhaul is taking longer than planned because Alstom is the sole contractor qualified to replace the aging proprietary subsystems that have powered the Downtown Miami people-mover loop for nearly four decades, leaving Miami-Dade Transit with no competitive alternative and limited leverage over the project timeline. The single-vendor dependency has compounded scheduling difficulties and driven up oversight costs.
- The original completion deadline was May 2025; the new projected window is 2028–2029.
- Alstom holds exclusive knowledge of the system's proprietary infrastructure, making contractor substitution effectively impossible.
- The $15.5 million contract extension was approved by commissioners in January 2026 to maintain project oversight through the extended timeline.
What disruptions are Downtown riders experiencing right now?
The ongoing construction work has forced Miami-Dade Transit to shut down Metromover service every Saturday morning through at least the end of August 2026, a recurring inconvenience for commuters, residents, and visitors who rely on the free Downtown Miami loop. Weekend riders — including those accessing Brickell, the Arts & Entertainment District, and the central business core — are bearing the most direct impact.
- Saturday morning shutdowns are scheduled to continue through at least August 2026.
- No alternative free circulator service has been announced to offset the weekend gaps.
Is Miami-Dade County considering replacing the Metromover entirely?
Commissioner Raquel Regalado has publicly called for rethinking the Metromover from the ground up, disclosing that she has already held meetings with two companies — whose identities she has not revealed — that are interested in providing a next-generation replacement people-mover system for Downtown Miami. Regalado's remarks signal that at least one commissioner believes the decades-old infrastructure may not be worth saving.
- Regalado has not named the two companies she met with regarding a potential replacement system.
- No formal replacement proposal has been placed before the full commission.
- The county has not disclosed criteria or a timeline for any replacement evaluation process.